Tracking capex hours on project vs all hours

Avatar

Level 1
I have created a capex project which has both capex and non-capex tasks in it. i want to report on the capex hours as well as non capex hours for finance. is there a way to do this? Leslie Adams Books-A-Million, Inc.
1 Reply

Avatar

Level 10
Hi: Here is how we do it: We have a custom form we put on every task. It is called "Capital". It has a drop down with "Yes" and "No"; We set the capital flag appropriate to the work being performed; We run reports that divide baseline, current forecast, and actual hours by this capital flag (love that Matrix reporting capability); At a high level, that's how we do it. Thanks! Eric "http://www.crowley.com/"> Eric L Lucas , Manager IT PMO IT Governance and Quality | Information Technology o 904.727.4218 | m 904.377.4426 eric.lucas@crowley.com "http://feeds.feedburner.com/CrowleyNews"> "https://www.facebook.com/Crowley"> "http://twitter.com/crowleymaritime"> "https://www.linkedin.com/company/crowley-maritime"> "http://www.youtube.com/user/CrowleyMaritime"> "https://plus.google.com/+crowleymaritime"> "http://www.instagram.com/crowleymaritime">