The Adobe Workfront engineers are close to completing code that allows a scrum team to ignore date changes when adding a task or issue to an iteration. Currently after adding a task or issue to an iteration the 'start' and 'end' date change to that of the iteration. This new feature, if toggled on, would ignore the date changes and dates would not be affected at all when adding to an iteration.
This feature will under go heavy testing and that will include slowly rolling it out to customers. If anyone is interested in getting early access, please respond to this post or reach out to me by email at muir@adobe.com.
トピックはコミュニティのコンテンツの分類に役立ち、関連コンテンツを発見する可能性を広げます。
Yes, please! Our team has been eagerly waiting for this update and checking frequently since end of July.
Great. We will plan on included your Workfront instance.
Hi Patrick,
We are also excited aobut this change! We would like to be part of the testing.
Thank you.
Liz
Great. We will add your Workfront instance to the beta.
Great...when will testing start?
Hi Patrick,
Will this change be included in the 21.4 release in October?
Thanks.
Liz
表示
返信
いいね!の合計
@Patrick Muir - inactive‚ - just wanted to be sure you saw the above. Cheers!
表示
返信
いいね!の合計
This feature will get released to preview this Thursday. We can turn it on for your organization starting Monday, if you are comfortable after testing it in preview.
@liztarter - see above.
表示
返信
いいね!の合計
Thanks Patrick.
Copying in my system admin Jason Jones
@Jason Jones‚ ‚
@Liz Tarter‚
表示
返信
いいね!の合計
Hi Patrick, how do we explore the feature in Preview? I would like very much to try out this feature for my team.
表示
返信
いいね!の合計
Becky the feature should be live in preview this upcoming Thursday September 9.
表示
返信
いいね!の合計
Hi Patrick,
I'm in Preview. How do I turn this feature on? I've gone to my team>Edit and I don't see the functionality.
Thanks for your help!
表示
返信
いいね!の合計
I would check now in preview. If you go to to a team, that is toggled as an agile team, you should see a new section called "When a work item is added to an iteration:"
表示
返信
いいね!の合計
Patrick,
I tested this in Preview today.
One thing I noticed is that I cannot add predesssors to the tasks (stories) in the schedule. Two task are pulled into an iteration for one pod and 1 task is not pulled into an iteration.
Could it have to do with this new feature?
Thanks.
Liz
@Jason Jones‚
@Leigh Burger‚
表示
返信
いいね!の合計
Hi Patrick,
br
Quick question - when the new functionality is turned on for a team, will it impact tasks (stories) that already have a planned start and planned completion date? Meaning this does not work retroactively, correct? Only for tasks (stories) created AFTER the functionality is turned on?
br
Thanks.
br
Liz
br
@Leigh Burger
@Patrick Muir - inactive
br
br
表示
返信
いいね!の合計
Once the toggle is turned on, any task (regardless of when it was created) will not have the date changed when adding it to that teams iteration. But if you already added a task/issue to an iteration (without the toggle turned on), it will not change back to the original planned or completion date if you do toggle on the setting - this part is not retoactive.
表示
返信
いいね!の合計
Any chance this functionality can be added at the project level, maybe at the "add to iteration" step? Turning it on and off for all projects in a Pod could easily lead to applying when not wanted.
表示
返信
いいね!の合計
To clarify, the issue is having to toggle on the functionality for each individual scrum team versus enforcing it on the project level, so no matter what scrum team gets the assignment, the dates will be ignored?
表示
返信
いいね!の合計
IMO - do not want a universal setting that would affect all scum teams. The issue is toggling back and forth depending on the outcome you want for a project. My suggestion would be to enable a setting at the project level that lets you override the default setting you made for the scrum team