Hi,
Since expert in text code; so looking for a favour. We use assignment breakdown as column in project view, the code is;
displayname=Assignment Breakdown
listdelimiter=<br>
listmethod=nested(assignments).lists
textmode=true
type=iterate
valueexpression=CONCAT({assignedTo}.{name}," (",{role}.{name},") - ",{workRequired}/60,IF({workRequired}/60>ABS(1)," Hours"," Hour"))
valueformat=HTML
Id planned hours is 40 hrs equally between 3 assigments, then the planned hour shows 13.3333333 hrs each.
Any solution to round this number?????
Thanks in advance.
Mvh