I would love the Community's help in finding a solution our Task Template problem.
We have a task template that is pre-assigned to a design to quickly work on urgent / quick turnaround requests.
When a project is created, the project owner attaches the template.

The template is set up so that if a project is submitted PRIOR to 1130 am, all tasks will be assigned for same day.
1. However, we only want the designer to see the first task, not the Design Revisions or Prep Final files task. Currently the designer is seeing all three tasks.
The template is also set up so that if a project is submitted AFTER 1130 am, all tasks will be assigned NEXT business day.
The template is also set up so that if a REVISION or APPROVAL is given AFTER 1130, the tasks will be assigned NEXT business day.
We have discovered that the REVISION and PREP FINALS task are not showing up as expected. See below for descriptions.

Please let us know if you need further details. Happy to provide.