When a task in a project changes to a status (ie, In Progress, complete, etc.), can the row change to a color?
Solved! Go to Solution.
Yes, You have to edit your view.
When in edit mode, select the column and then "Advanced Options".
Then select "+Add Column Rule", When Task >> Status Equal (Choose whatever status you want)
Background (select a colour)
Select "Apply to entire row"
TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use.
If you like my content, please take a moment to view and vote on my Idea Requests: https://tinyurl.com/mysocalledideas
Views
Replies
Total Likes
Yes, You have to edit your view.
When in edit mode, select the column and then "Advanced Options".
Then select "+Add Column Rule", When Task >> Status Equal (Choose whatever status you want)
Background (select a colour)
Select "Apply to entire row"
TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use.
If you like my content, please take a moment to view and vote on my Idea Requests: https://tinyurl.com/mysocalledideas
Views
Replies
Total Likes
I can do that in a report, how about in the actual 'template' task that is added to the Project?
Can that change?
Views
Replies
Total Likes
You can edit the View on projects in the same way - and you'll see your color on all completed tasks on any project where you use that same View
Views
Replies
Total Likes
Thanks, that makes sense, please ignore my comments above
Views
Replies
Total Likes
Remember: when you're looking at the tasks of a project, you're looking at a task report.
Views
Replies
Total Likes
But the tasks are made from a 'template'. I can't change the color of a row when a new status is selected on a task.
Views
Replies
Total Likes