Hey WF forum,
Wondering if anyone has any thoughts on how to solve my current situation! Here we go....
Basically I'm trying to keep tasks durations as close to a realistic calendar as possible when assigning tasks. In this example, let's assume my project tasks are timed and sequenced appropriately with predecessors, etc. and my project is complete aside from assigning out tasks.
Now, once I begin assigning team members to their tasks, the durations change according to what that specific team member is currently working on (as you'll see in my screenshot attached.)
- Test Task w/out Assignment has a duration of 6 weeks; starting 3/22 and ending on 5/3 (ideal)
- Test Task w/ Assignment has a duration of 6 weeks; starting 3/22 but ending on 4/23 (not ideal)
As you can tell, the second bullet skews the timeline by about a week and a half which I'm trying to avoid. I've tried changing the 'Duration Type' between Calculated Work / Assignment, Effort Driven, and Simple to no avail.
Any thoughts on how to override whatever logic WorkFront is using to calculate the duration when a team member is assigned?
Appreciate all insight in advance!!