Hi there!
Our company works with a third-party team in a different timezone. Whenever the project manager of that team assigns one of those members to a task, the task dates automatically adjust to the following day. We don't seem to have any issues like this when assigning tasks to users in our country so I assumed this was an issue with their accounts being set up to their timezone. Because they're working on our hours anyway, I've readjusted their accounts to fall under our timezone but unfortunately, this issue continues to persist. Has anyone else had an issue to similar to this or suggestions to what else I should look into? Thanks! Diana Dizon