Expand my Community achievements bar.

SOLVED

Resources Overallocations for projects

Avatar

Level 3

Hi Community,

Any idea why Workfront will be showing resources overallocations on the workload balancer when the resources is 100% allocated across two projects (i.e., 2977 is 25% and 2979 is 75%)?.  Jan 16.48hrs, Feb 16.05hrs, and March 16.05 hrs over allocations. please see screenshot below and your input is super appreciated. 

 

meshackOm_0-1706200809430.png

 

1 Accepted Solution

Avatar

Correct answer by
Level 7

If you hover over the red box, it shows capacity vs planned hours for that period. That might give you a hint.

You should also consider checking User Schedule and Work Time (in user profile settings).

View solution in original post

1 Reply

Avatar

Correct answer by
Level 7

If you hover over the red box, it shows capacity vs planned hours for that period. That might give you a hint.

You should also consider checking User Schedule and Work Time (in user profile settings).