Resource Report Overview

Avatar

Level 2
Hi - I was wondering if anyone else experienced this: On the Resource Report Overview, we see the red cell but no planned/actual hours appear. When I expand the person, I can see the hours in the projects they are on. Any ideas why the hours wouldn't show? Thanks - Celeste Celeste DiDio PwC FL
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10
Hi Celeste, After a bit of digging around, I found an example in our system. The cause seems to be that the resource's schedule had a non-working day exception (i.e. public holiday). The legacy resource planner is not showing the planned hours for this day, even though there were indeed planned hours for that day. Interestingly, this logic was carried over to the new Calendar tools, but I believe they are going to change it to show planned hours even if the user is on a day off / schedule exception. Regards, David Cornwell