Hi Celeste, Based on "https://support.workfront.com/hc/en-us/articles/216735948-Using-the-Resource-Grid#preferences-icon">this article , I suspect that the Summary Tasks you expected to see on the Resource Grid are falling through the cracks due to a technicality of some kind. In particular, each such Task must have:
Planned Duration greater than 0.
Planned Start Date and Planned Completion Dates different from one another. (If they are the same, the Planned Duration is 0).
Planned Hours greater than 0.
If those Summary Tasks meet all these rules, perhaps there is another in the article still in play; but otherwise, I'd then recommend you raise a ticket with Workfront. Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand!