Hello!

We have a "My Requests" report (see screenshot) that shows the original request, the converted project, status, etc. The status automatically feeds off of the Project status, however the Planned Completion Date (Due Date in our case) is set to the Request which is always different. If I switch it to the Project Planned Completion Date, it is not accurate. How do we create a Due Date column that pulls the Converted Project's Planned Completion Date?

Thanks in advance!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

Converted project information should all be under the "Resolve Project" section of your "field picker".

i.e. If you were editing the report and you clicked on the Converted Project Name column of your view, you should see that this is the Name field under the Resolve Project section.

All your other converted project fields would also come from this one section (resolve project name, resolve project status and resolve project planned completion date).

1 reply

skyehansen
Community Advisor
skyehansenCommunity AdvisorAccepted solution
Community Advisor
March 19, 2021

Converted project information should all be under the "Resolve Project" section of your "field picker".

i.e. If you were editing the report and you clicked on the Converted Project Name column of your view, you should see that this is the Name field under the Resolve Project section.

All your other converted project fields would also come from this one section (resolve project name, resolve project status and resolve project planned completion date).

March 22, 2021