Hi Community,
I want to create a report to identify assigned resources for project tasks but they are NOT actually being used or utilized for the project. The only way I can view this now is through resources utilization. But I want to create a report that I can use to pull those un-utilized assigned resources.
Any suggestion would deeply appreciated.
Thanks.
Mesh
해결되었습니다! 솔루션으로 이동.
조회 수
답글
좋아요 수
Hi, you can pull a 'Timesheet' Report (one of the report type options) and have filters like this to show timesheets NOT submitted. Can group by owner to see people who have not submitted timesheets, which could indicate they have not tasks to log time to. This is only a viable option if you submit timesheets and log time. If you log time but don't submit, you could add a filter for Timesheet > Total Hours is less than X.
조회 수
답글
좋아요 수
Hi there, does your organization track time? You could do a timesheet report of timesheets not submitted by week or by user to indicate people that aren't logging time/have no tasks to log time to?
조회 수
답글
좋아요 수
@Madalyn_Destafney thanks for your input.
Yes, we track time to logged to everyone task assigned to resources. Your idea sounds very promising. Please how do I create the timesheet report to identify users or resources aren't logging time or no tasks to log time to?
Thanks again.
Mesh
조회 수
답글
좋아요 수
Hi, you can pull a 'Timesheet' Report (one of the report type options) and have filters like this to show timesheets NOT submitted. Can group by owner to see people who have not submitted timesheets, which could indicate they have not tasks to log time to. This is only a viable option if you submit timesheets and log time. If you log time but don't submit, you could add a filter for Timesheet > Total Hours is less than X.
조회 수
답글
좋아요 수
@Madalyn_Destafney excellent! thank you so much. Sorry for replying late. I was on vacation.