Task Based Workload Balancer

  • September 20, 2023
  • 1 reply
  • 728 views

Hi, there! 

My team is an in-house marketing department. I am looking for a way to adjust workload balancer, or a report to build that be a work around, to show workload based on number of tasks assigned to each person on the team. We do not record hours in WF currently, so the resource managing resources aren't as helpful right now as I am trying to see what everyone's current load is. If the adding and tracking hours to task is the only, we may not be apposed to the switch, but I, the project manager, am just trying to find another alternative first that wouldn't require introducing a major addition or change to the team. 

Thanks! 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

I think you just want a task or assignment report (if multiple people are assigned to a single task, go with assignment report), filtering for incomplete tasks that are assigned to your team. If for example, you group it by planned completion date (week) and then by who it's assigned to, then you have a way to see how many tasks everyone is working on that is due that week. It's not ideal, but as you say, it's a workaround.

1 reply

skyehansen
Community Advisor and Adobe Champion
skyehansenCommunity Advisor and Adobe ChampionAccepted solution
September 20, 2023

I think you just want a task or assignment report (if multiple people are assigned to a single task, go with assignment report), filtering for incomplete tasks that are assigned to your team. If for example, you group it by planned completion date (week) and then by who it's assigned to, then you have a way to see how many tasks everyone is working on that is due that week. It's not ideal, but as you say, it's a workaround.

Halie_Baer
Level 2
September 20, 2023

Thank you! I was able to create a task report, group by name, and then add a chart that grouped by record count for that visual. This will work great for the time being.