Report for the total actual duration between two not consecutive milestones | Community
Skip to main content
Level 2
April 22, 2021
Question

Report for the total actual duration between two not consecutive milestones

  • April 22, 2021
  • 1 reply
  • 457 views

Hi All - I am trying to create a report that shows the total duration between two milestones (for example - the total time between the Build Milestone and the Go Live Milestone, but I don't need the timing before plan or after go live, so I don't want to use the actual project duration).

How do I pull a report that shows me the total time between two milestones?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
April 22, 2021

Hi Laura,

One approach is to use the technique I invented in my Going the Extra Milestones blog post.

Regards,

Doug