Quick Tip: Check your task constraints when you can't figure out why your timeline isn't updating or the predecessors don't seem to be affecting dates correctly.

Avatar

Employee

Remember that task constraints affect how dates populate and whether they are taking predecessors and durations into account. Remember that manually selecting dates will update the task constraint to "Must Start On" or "Must Finish On" (unless the constraint is already set to Fixed Dates).

トピック

トピックはコミュニティのコンテンツの分類に役立ち、関連コンテンツを発見する可能性を広げます。

5 返信

Avatar

Level 10

0694X00000C1KHBQA3.gif

Avatar

Employee

Haha! Right? It can be so frustrating sometimes, then you check and you're like - AH! It got switched from "As Soon As Possible"... I get tripped up by this often!

Avatar

Level 10

We actually have two views for people to use to quickly check. One has the task constraint column showing and another highlights a row when the task constraint is not As Soon As Possible. We then have trained people to switch views first to see if that is the issue first.

Avatar

Level 10

You've trained people to self-troubleshoot?

 

*faints*

Avatar

Employee

yes