project recalculation of timeline issues?

Avatar

Level 10
I have my settings "automatic and on change" - however the recalculation is not happening. I have to manually do a project timeline recalculation. Is anyone else experiencing this problem? Is this a known bug?
6 Replies

Avatar

Level 10
Hi: I don’t trust WorkFront to consistently recalculate custom expressions - or to recalculate dates or finances. I am incessantly select Project Actions, recalculate timeline and/or recalculate finances. I also frequently select all tasks and then edit and then recalculate custom expressions - just to be sure it gets done. I recall hearing once, some time back, that the thread that should do the recalc sometimes doesn’t run. It gets stuck or dies a quiet death or something. I make sure everything is up to date by manually recalcing everything. Look, I probably don’t need to do all that recalcing. I just do it to rule out a problem with the auto-recalc process. Thanks! Eric

Avatar

Level 10
Yes, we have to go in and force recalculate timeline often. Seems to be especially so when a PM has a lot of changes to make to a schedule. Although our projects are set to recal 'automatic and on change' - it doesn't. :(

Avatar

Level 10
is there a way - to select multiple projects and manually recalculate their timeline - vs 1 by 1 - as I have over 100 projects...

Avatar

Level 10
Benetta, if ensuring that your calculated parameters are up to date is important, I invite you to try our Recalc Helper , which can do up to 50,000 objects in a single run. Regards, Doug

Avatar

Level 10
Doug, Okay. Thank you. [image: APS Payroll logo] Benetta Perry New Client Setup Specialist p: 318-222-9774 f: 318-222-0601 e: bperry@apspayroll.com www.apspayroll.com < ">http://www.facebook.com/apspayroll> < ">https://twitter.com/apspayroll> < ">https://plus.google.com/u/1/101565211370298693012/posts> < ">http://www.linkedin.com/company/aps-payroll> The information contained in this transmission may contain privileged and confidential information. It is intended only for the use of the person(s) named above. If you are not the intended recipient, you are hereby notified that any review, dissemination, distribution or duplication of this communication is strictly prohibited. If you are not the intended recipient, please contact the sender by reply email and destroy all copies of the original message. On Tue, Feb 14, 2017 at 1:15 PM, ....Doug.... Den Hoed < globalforum@communitylists.workfront.com> wrote: > Benetta, if ensuring that your calculated parameters are up to date is > important, I invite you to try our Recalc Helper > http://store.atappstore.com/product/recalc-helper, which can do up to > 50,000 objects in a single run. > > Regards, > > Doug > > -----End Original Message----- >

Avatar

Level 8
Hi Benetta, I would create a project report, select all, then Recalculate Timelines. Adina ________________________________