Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Project percent calculation - global setting

Avatar

Level 1
We have 2 types of projects – ones that are done in house, where it makes sense to base the project percentage on the hours worked – and ones that are done by external contractors, where it makes sense to base the project percentage on the duration. Trouble is this is a global setting in Workfront Has anyone found a way to get around this so it can be changed per project ? Thanks Adrian Lyndon DE Electronics Section Manager "https://www.ametek-land.com/"> Office: +44 (0)1246 581427 Address: AMETEK Land, Stubley Lane, Dronfield Derbyshire, S18 1DJ England E-mail: mailto:adrian.lyndon@ametek.com | Web: "https://www.ametek-land.com/"> https://www.ametek-land.com "https://www.ametek-land.com/contactus/keepinguptodate">
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 3

Hello Adrian,

Currently there is not a way to use both of these settings for Percentage, it will need to be one or the other.