Project Budgeting and Resource Pools | Community
Skip to main content
Level 2
January 30, 2025
Solved

Project Budgeting and Resource Pools

  • January 30, 2025
  • 1 reply
  • 395 views

Our IT PMO is launching a process for IT project budget management and reporting using Workfront.  This includes labor hours, labor cost, and expense, as well as budget, plan, and actual for each. 

Each IT role has been set with an hourly rate.

We had been using one large companywide resource pool, and teams have been using Planner to manage resources - availability, planned, and actual hours.  

Having only one large companywide resource pool presented a couple challenges. 

First, when entering a resource labor budget within the Resource Budgeting section of the Business Case, a long list of companywide roles was listed, making it very unwieldy for a project manager to enter budgeted hours.  Having only 3 months to enter data didn't help.  This would require a lot of scrolling and page turning. 

Second, only IT roles have rates.  Adding a budget to a role that doesn't have a rate would translate to $0. 

Therefore, it was advantageous to create an IT-only resource pool, assign that pool to the project, and remove the companywide resource pool.  By doing so, the Resource Budgeting list was much shorter as it was limited to IT resources only, and when entering budgeted hours at the project level, Workfront distributed the hours across IT roles only ensuring all hours calculated a labor cost.   

After reading this communities comments on resource pools, it seems they are a bit of a mystery.  It's good to know I'm not alone.  I thought I would share this information as a good use case for resource pools.  On the other hand, I'm a bit nervous about any unforeseen impacts of removing the companywide resource pool from the project and replacing it with the IT-only resource pool.  It doesn't seem to impact having the ability to add task assignments to resources outside of the IT-only resource pool, so that's good.  

Does anyone have any thoughts of potential impacts we should be aware of?  Thanks in advance.  

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

Resource pools are basically only used for Resource Planner. I've pondered and asked this question many times - "why do we need resource pools" since it's just one more thing to manage. It always seems to come back to "because you need them for Resource Planner". So, it's a never-ending circle of need. 🙂

 

Adobe recommends updating resource pools as people come and go so there is always an accurate list of resources. Because of this, I don't envision you running into issues with changing up the resource pool from all to some.

 

 

1 reply

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
February 4, 2025

Resource pools are basically only used for Resource Planner. I've pondered and asked this question many times - "why do we need resource pools" since it's just one more thing to manage. It always seems to come back to "because you need them for Resource Planner". So, it's a never-ending circle of need. 🙂

 

Adobe recommends updating resource pools as people come and go so there is always an accurate list of resources. Because of this, I don't envision you running into issues with changing up the resource pool from all to some.