Hi Mesh,
Yes, you are spot on. Workfront is basically telling you that the project is "at risk" of being late, because there are tasks that should have started but have not. Because these tasks haven't started, Workfront is estimating/projecting that the project is going to complete later than that planned completion date.
You can read more on this here.
Best Regards,
Rich.