Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!
SOLVED

Priority set at project level but it doesn't cascade to a request.

Avatar

Level 1

I've set the Priority field on a project that contains Requests. It's not filtering down to the request.  How do I set that?

 

Background:   I have 3 projects that will contain requests.  I want any requests opened under Project A to assign the same priority as given to the project.

Project A has a priority of Urgent.

Project B has a priority of High.

Project C has a priority of Normal.

So that when requests are entered, the assignee will know that a request under Project A has a higher priority than a request assigned under Project C.

 

Thoughts?

1 Accepted Solution

Avatar

Correct answer by
Level 10

Hi @jwc7 

In our organisation, we pulled those request in a report group under projectwise. This shows the priority of individual request. And the grouping has its own priority, talking about project. 

 

View solution in original post

1 Reply

Avatar

Correct answer by
Level 10

Hi @jwc7 

In our organisation, we pulled those request in a report group under projectwise. This shows the priority of individual request. And the grouping has its own priority, talking about project.