Priority set at project level but it doesn't cascade to a request.

Avatar

Level 1

I've set the Priority field on a project that contains Requests. It's not filtering down to the request.  How do I set that?

 

Background:   I have 3 projects that will contain requests.  I want any requests opened under Project A to assign the same priority as given to the project.

Project A has a priority of Urgent.

Project B has a priority of High.

Project C has a priority of Normal.

So that when requests are entered, the assignee will know that a request under Project A has a higher priority than a request assigned under Project C.

 

Thoughts?

1 Accepted Solution

Avatar

Correct answer by
Level 10

Hi @jwc7 

In our organisation, we pulled those request in a report group under projectwise. This shows the priority of individual request. And the grouping has its own priority, talking about project. 

 

View solution in original post

1 Reply

Avatar

Correct answer by
Level 10

Hi @jwc7 

In our organisation, we pulled those request in a report group under projectwise. This shows the priority of individual request. And the grouping has its own priority, talking about project.