Expand my Community achievements bar.

Submissions are now open for the 2026 Adobe Experience Maker Awards.

Planned Hours column formatting

Avatar

Level 2

Below is the current text mode for the Planned Hours column in my project report and how it is showing when I run the report. Is there a way I can update the code to have it show 13,798.75 (which adds a comma and removes the word 'Hours')?? The Actual Hours column shows the format I want without changing the code (added this image below as well) but I can't seem to figure out the code to get the Planned Hours to show the format I want. 

 

aggregator.displayformat=minutesAsHoursString
aggregator.function=SUM
aggregator.namekey=workrequired
aggregator.valuefield=workRequired
aggregator.valueformat=intAsInt
linkedname=direct
namekey=workRequired
querysort=workRequired
valuefield=workRequired
valueformat=compound
viewalias=workrequired

LauraMC_1-1757953274274.png

 

LauraMC_2-1757953495486.png

 

Thanks in advance!!

 

3 Replies

Avatar

Community Advisor

Hi there, in your project report > planned hours column, try replacing your text mode completely with this:

displayname=Planned Hours
valueexpression={workRequired}/60
valueformat=doubleAsDouble

Let me know if that's what you're looking for! 

If this helped you, please mark correct to help others : )

Avatar

Level 2

Hi Madalyn - 

 

Yes, that code worked for the field within the Details tab on the report. However, I'm trying to get that field column settings to 'Summarize this column by:' = 'sum' for the Summary tab on the report. Any suggestions for code to get it to sum all the data?? 🙂

Avatar

Community Advisor

Hi, not sure I'm following. In the advanced options of that hrs column in details view, do you have it on sum?
I don't think you can modify the language in the Summary tab of the report if that's what you're asking? If you summarize it by Sum in details, it should sum in Summary too.

If this helped you, please mark correct to help others : )