New Calendar FUN-ctionality request/bug

Avatar

Level 5

I don't know where to put in a bug report, or maybe this is a feature issue.

When adding a range of custom dates into a calendar to populate tasks, it seems that both the start and end (or date 1 and date 2) must be populated -- otherwise the task won't populate.

Why is this an issue?

Let's use a religious holiday as an example. Most are one day holidays, but some span a period of time. It would be ideal if Workfront said "if date 2 = blank then ignore" and only populate the task for date 1. That way, single date holidays, or other ranges, can populate without having to double enter a date 1 and date 2 for ever task/item.

Thanks.