Expand my Community achievements bar.

Interested in getting an Adobe Workfront certification? Don't miss our AMA on June 10th, where our experts will be available to answer any questions you may have about getting certified!

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

New Calendar FUN-ctionality request/bug

Avatar

Level 5

I don't know where to put in a bug report, or maybe this is a feature issue.

When adding a range of custom dates into a calendar to populate tasks, it seems that both the start and end (or date 1 and date 2) must be populated -- otherwise the task won't populate.

Why is this an issue?

Let's use a religious holiday as an example. Most are one day holidays, but some span a period of time. It would be ideal if Workfront said "if date 2 = blank then ignore" and only populate the task for date 1. That way, single date holidays, or other ranges, can populate without having to double enter a date 1 and date 2 for ever task/item.

Thanks.

@Jonathan Yu‚ @Lynne VanHyning‚

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

0 Replies