I have a template that maps a project 9 months out. Often times, we end up not kicking off a project until 5 months out.
When this happens, I go in and manually adjust the timeline so that the durations are evenly reduced and distributed. Is there a way that the template can automatically do this?
Right now the template is set up as a "start from" but I have a fixed deadline that all my tasks work back from. So, if I use my 9 month template but my timeframe is only 5 months, it just has the first third of my tasks all overlapping and due at the same time.
Thanks in advance!
Topics help categorize Community content and increase your ability to discover relevant content.
This wins question of the month. Following to see if anybody has a clever answer.
Views
Replies
Total Likes
I'll bite, Jill: my answer is No.
But.
Although there is no native way to compress a schedule within Workfront as such, there are some workarounds that might be close enough:
Regards,
Doug
Views
Replies
Total Likes