Lock or Freeze Allocations

Avatar

Level 1

Is there a way to "lock" or "freeze" allocations to the day/week/month in which they are assigned even if the dates shift? Think of it like using a "$" in an excel formula to lock something in place. 

  • As a resource manager, I allocate the hours based on discussion with my team member. 
  • As a project owner, I added planned hours, added other users, or I adjusted the dates of the task because others need to start work earlier or end later.
  • The change made adjusts the allocation efforts the resource manager did. The resource manager set the allocations in the day/week/month specifically and does not want it to change. Can this be locked? 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Community Advisor

 

Hi @Greta_12-25,

 

I've cued up this video to highlight a native-Workfront technique @ScottMo1 and I developed (as part of our Lite-Brite solution) that I believe you could use to accomplish your "Lock or Freeze Allocations" requirement...particularly if you also consider using it in conjunction with Workfront's Baselines feature.

 

Regards,

Doug