Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

Kanban board

Avatar

Level 2
Is there a way to show the percent complete on a project when using the Kanban board? i.e. all of my stories for the project are in the kanban board. P. Philip Rinehart New York University
1 Reply

Avatar

Level 8
If I understand your question correctly, yes. You can add additional fields to your card tiles on the board. In this case, you can add the Project --> Percent Complete field, so when you are looking at your stories on the board, you can see what the overall project percent complete is. Terry Hynd EBSCO Information Services