It appears that tasks can be started and completed without completing the applicable task's predecessor

Avatar

Level 3

It appears that tasks can be started and completed without completing the applicable task's predecessor.

 

How can I configure Workfront to prevent this type of behavior and enforce a user to first complete the Task's predecessor?

 

Or, is this a bug?

1 受け入れられたソリューション

Avatar

正解者
Community Advisor

HI,

 

You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.

 

When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.

 

Best Regards,

Rich. 

元の投稿で解決策を見る

2 返信

Avatar

正解者
Community Advisor

HI,

 

You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.

 

When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.

 

Best Regards,

Rich. 

Avatar

Level 3

Thank you so much!