In our previous system there was an option "All Members" to send the entire group working on the project status updates. I wasn't sure if WF had this functionality. Thanks!
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Hi Jeanine,
Yes, there is the abiliy to update the project team in Workfront. It's slightly different depending on if you are using the new workfront experience or classic.
If you are using the NWE, when in the project, navigate to the people tab (in the left hand panel). From this screen you have the ability to send an update to all project team members.
In Wokfront Classic, when in the project, navigate to the staffing tab and then the people sub tab, from there you also have the ability to send an update to all project team members.
Hope this helps!
Best Regards,
Rich.
Hi Jeanine,
Yes, there is the abiliy to update the project team in Workfront. It's slightly different depending on if you are using the new workfront experience or classic.
If you are using the NWE, when in the project, navigate to the people tab (in the left hand panel). From this screen you have the ability to send an update to all project team members.
In Wokfront Classic, when in the project, navigate to the staffing tab and then the people sub tab, from there you also have the ability to send an update to all project team members.
Hope this helps!
Best Regards,
Rich.
That works! Thank you!
Views
Replies
Total Likes
Thats a good tip. Thanks to Richard.
Views
Replies
Total Likes
Views
Likes
Replies
Views
Likes
Replies
Views
Likes
Replies
Views
Likes
Replies