Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Hi Kelly,
Rich is correct, except that using a template isn't the only way to accomplish this.
In the Project Settings, you can add a custom form that will automatically be associated with every new task that is created in the project. The catch is, if you already have tasks in the schedule, you will need to bulk edit them to add the form.
Hope this helps,
Teale
Hi Kelly,
If you create your projects from a template, then yes you can automatically add custom forms to every new task that is created. In the projecttemplate settings you can specify a task default custom form (see screen shot below). Then, when you spin up a project from this template, any new tasks that you add to the newly created project will automatically have the default task custom form that you specified in the template settings attached to it.
As far as I am aware, this is only possible when creating projects from a template.
Best Regards,
Rich.
Thanks Richard! But I'm looking for a way to add/create new Tasks.
Views
Replies
Total Likes
Hi Kelly,
The custom form would automatically be applied to any new tasks that you add / create on the project as well. So long as your project was originally created from a template where the default task custom form was set, any brand new tasks that you add to that project will also have the custom form automatically applied.
Best Regards,
Rich.
Hi Kelly,
Rich is correct, except that using a template isn't the only way to accomplish this.
In the Project Settings, you can add a custom form that will automatically be associated with every new task that is created in the project. The catch is, if you already have tasks in the schedule, you will need to bulk edit them to add the form.
Hope this helps,
Teale
Thanks Teale! Every day's a school day! 😁
Teale, that's exactly what I was looking for - thanks to you both!
Views
Replies
Total Likes
Hey Teale,
Can I associate a custom form just to one specific task in a template? I don't need to be attached to every task or new tasks?
Best,
Daniela
Views
Replies
Total Likes
Hi Daniela,
Yes, you can add the form to the task in the template and it will apply to all projects when they're created. If you need to add it to the individual task on existing projects, just run a task report where the name contains "task name" and you can bulk edit to add the form.
Hope this helps,
Teale
Views
Replies
Total Likes
Thank you!
Views
Replies
Total Likes
Views
Likes
Replies
Views
Likes
Replies
Views
Likes
Replies