Is there a way for an Admin to update users' tasks status in bulk?

Avatar

Level 2
We have some old tasks that were not checked off in the beginning of our use of WF- is there a way that Admin can change the status of the task- without "completing" the project? Julie Ohman - WF user since May 21, 2018
1 Reply

Avatar

Level 10
Yes. Under Edit Project > Settings change the Completion Mode to Manual. Then close as many Tasks as you wish (bulk edit – I assume). The Project won't go Complete until you change the Status. Vic Alejandro, PMP, CSM | IT Program Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/"> http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT