Expand my Community achievements bar.

The Community Advisors application is now OPEN for the second class of 2024. Apply to become a part of this exclusive program!

Is there a setting where when I open my Project that tasks are all Collapsed?

Avatar

Level 10
Is there a setting where when I open my Project that tasks are all Collapsed?
3 Replies

Avatar

Level 10

0690z000007ZkMVAA0.pngHi Benetta,

I am not aware of any global setting to do this. However, if you use the collapse-all button at the top of the task list, and navigate away to another project and then back, it should remain collapsed. Workfront remembers how you left it per-project.

Regards, David0690z000007ZkPEAA0.png0690z000007ZkPTAA0.png

Avatar

Level 7
Yes, and of course any tasks you collapse and not collapse will be remembered. However, this is only for your current session. Once you log out and back in, they all expand.

Avatar

Level 2
We need to establish user profiles that can reside on the server so we can preserve settings & preferences. Storing these on client side cache is less storage perhaps (but the price of storage compared to the price of frustration, it's a no brainer).