Insert Task

Avatar

Level 2

Hello,

 

Currently when I insert a new task, the task appears at the bottom of the task list / project plan.  And I have to manually move it to the desired location.

 

Is it possible to insert a task anywhere in the plan or is it forced to be inserted at the bottom?

 

Thank you,
- Andrew.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Right click in the light blue area where the task number is:

Screenshot 2023-05-31 at 11.06.09 am.jpg

make sure your task list is sorted by task number or it limits a lot of actions.

 

TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use.

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

Right click in the light blue area where the task number is:

Screenshot 2023-05-31 at 11.06.09 am.jpg

make sure your task list is sorted by task number or it limits a lot of actions.

 

TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use.