Hi Helen,
Are all of your default durations days? If so you could use this:
linkedname=direct
name=Default Duration
querysort=defaultDuration
textmode=true
valuefield=defaultDuration
valueformat=int
Hope that helps!
Views
Replies
Total Likes
Thank you Sarah - but this not produce any results on my report.
Views
Replies
Total Likes
Are you using a Queue Topic report or a Queue report?
Views
Replies
Total Likes
I am actually using an Issue report. I will try a queue report -- thx
Views
Replies
Total Likes
Try using this on the Queue report:
linkedname=direct
name=Default Duration
querysort=defaultDurationExpression
textmode=true
valuefield=defaultDurationExpression
valueformat=string
Views
Replies
Total Likes
HI Sarah
I needed the data reported at the issues not project level. Your calc works on the queue topic report - but I need the issue report to pull is request specific data
Views
Replies
Total Likes
Gotcha - do you have your default hours on each queue topic or just in the queue details default duration? If you have it on the queue topic, this will work:
linkedname=direct
name=Default Duration
querysort=queueTopic:defaultDurationExpression
textmode=true
valuefield=queueTopic:defaultDurationExpression
valueformat=string
If you have it on the queue details, this will work:
linkedname=direct
name=Default Duration
querysort=project:queueDef:defaultDurationExpression
textmode=true
valuefield=project:queueDef:defaultDurationExpression
valueformat=string
I tried making an expression to combine these (if the queue topic duration is blank, use queue duration), but I don't think you can go three levels in expressions.
For some reason, I can't tag people right now, but you could try tagging Anthony Imgrund in this and he could confirm that this isn't possible or if I just have my syntax wrong:
linkedname=direct
name=Default Duration
textmode=true
valueexpression=IF(ISBLANK({queueTopic}.{defaultDurationExpression}),{project}.{queueDef}.{defaultDurationExpression},{queueTopic}.{defaultDurationExpression})
valueformat=HTML
Views
Replies
Total Likes
Sarah - thank you - that worked on the report. I am meeting with WF Support tomorrow - I would really like to be able to capture the data in a calculated custom field so that I can use it in other calculations. If I learn anything new I will share it here