Expand my Community achievements bar.

How to log half days in WF without disturbing the project schedule

Avatar

Level 1

Hi we need to enter specified hours for tasks in the project for user. Also if we can add multiple schedules in our project set up? 

1 Reply

Avatar

Community Advisor

Preeti123, here is link to EXPL tutorial on creating schedules, https://experienceleague.adobe.com/docs/workfront-learn/tutorials-workfront/administration-and-setup...  You can input holidays, half days, etc. within the schedule and assign it to the users that need it.  The usual default set up in the Workfront system is to use the user's schedule, meaning the project timeline will respect the user's schedule they have set in their profile.  

You can only have one schedule for a project, not multiples.