Hi everyone,
Does a user's Worktime need to match the schedule? For instance, if we operate with a 40hr week schedule, does user's work time need to be set to 1?
If we change our worktime to .75 to account for shrinkage (meetings and etc.) what else would need to be changed in the system to ensure projects aren't negatively impacted?
Thank you!
Views
Replies
Total Likes
Hello @mvsteep
I think its difficult to say what the impact across your instance would be.
From my experience it can affect time frames on tasks and projects etc.
What I would do is test it in preview and see what the changes impact. Hopefully not to much and the you can sort production out.
Good luck
There is a project setting that says something like "Do not let user time off affect project timeline" or something like that. I would keep that checked.
I would then assign a critical path task to a person that has their FTE and Work Time set to 1, then screenshot the timeline. Then change their FTE to something drastic like .2 and see if the timeline changes. Then set their work time to something drastic like .2 and see if that affects the timeline.
Maybe after doing that, you could report the results back here so everyone can benefit from that knowledge.
Views
Replies
Total Likes
I'll test that scenario out, thank you!
Views
Replies
Total Likes
Work time doesn't impact project schedule as far as I can tell, nor is it supposed to. Read the link below to see if it helps:
The way I think of it is, work time helps me in the resource management area by showing me how over/under a specific assignee is. I can use it to see that the user was assigned to 20 hours of work this week, but that they are still under water because their work time was set to 0.25 so they are really only available for 10 hours. But it doesn't change the project schedule to make sure the user can fulfill the task.
But, @skyehansen, shouldn't it impact automatic resource leveling? For example, if we have told Workfront that a given user is only available for 75% of their work schedule (e.g., 6 hrs out of an 8 hr work day), then shouldn't resource leveling take that into account and space tasks out on the timeline based on a 6 hrs/day availability? It seems like this should be core functionality because, in my mind at least, that was the whole benefit of having a feature like this.
Views
Replies
Total Likes
I don't believe resource leveling was in scope of the original question, but please feel free to post separately if you have a question about this, detailing your exact experience and steps to get there -- it's always possible it might be an error in your configuration somehow.
I will mention though, that if you feel as though something in workfront isn't working as intended, I recommend submitting a case to Workfront Support for this. If they confirm it is working as desired then your next step would be to add an Idea for customers to vote on.
Views
Replies
Total Likes