Hi Doug!
First, thanks for trying to help!
I am using Baselines. Although as far as I have found that only captures Revenue/Cost at the task level, not the project level. (I know it captures hours at the project level.)
Also, while I do adjust hours as a project progresses, using Planned hours does not work for comparing vs baseline unless I am manually changing all PAST planned hours to match actual billed hours. On a large project that is unmanageable- Unless there is a feature that does this automatically?
Super simple example:
Project Baseline: 3 hours Total
Task 1 (last week): Plan was 1 hour; Actual billed: 2 hours
Task 2 (This week): Plan is 2 hours, will still need 2 hours so I can't reduce
My Plan still matches my Baseline, which implies I'm on budget.
But in reality I will be 1 hr over budget for the project.
This example also doesn't factor in various charge out rates for different roles OR plan vs actual expenses.
So what I really need is a PROJECT level financial comparison of
baseline costs vs (Actual costs + FUTURE Planned costs)
This is what I really need help calculating. Any ideas?
I am getting a little closer to solving this, and will share if I figure it out. Any help is appreciated!
One related problem- is there any way to filter ONLY ONE field in a report using text mode?
(again, I'm new, so it's entirely possible that I'm misunderstanding how to use some basic features that do all this...)
thanks
Brad