Hi, I need to match the customised date field (Creative Due Date) to the Planned Completion Date and have been wondering if I could use the calculated field for this purpose. I have a Creative Due Date in the issue custom form that marketing folks are inputting and would like this date to be automatically also the Planned Completion Date for the issue once submitted. Is that possible? I never used calculated fields so shooting in the dark. Any suggestions will be greatly appreciated. Marta

4 Replies

Avatar

Community Advisor

You can create a calculation for your custom field that pulls in the Planned Completion Date. Paste the following into your calculation: 

 

 

{plannedCompletionDate}

 

Screenshot 2023-08-31 at 1.41.24 pm.jpg

TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use.
If you like my content, please take a moment to view and vote on my Idea Requests: https://tinyurl.com/mysocalledideas

 

Avatar

Community Advisor

@MartaSo are you converting your issues into tasks? Projects? @RandyRoberts your response was my first thought too but if this is converted to a task or project then we’d need to tweak this approach?

If this helped you, please mark correct to help others : )

Avatar

Level 4

@Madalyn_Destafney No we do not convert issues to tasks or projects for this specific team so I am not concerned about project timelines. 

Avatar

Level 4

@RandyRoberts that's fantastic! I am going to try this for sure! thanks so much