Hello! I am trying out the Workload Balancer but can anyone tell me why hours for tasks that are completed are showing for the workers?

Avatar

Level 3
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

"Why" I can't say. But looks like with the 20.4 release you'll be able to show or hide completed work

https://one.workfront.com/s/document-item?bundleId=workfront-classic&topicId=Content%2FProduct_Annou...

Avatar

Level 10

Highly recommend turning on the Projected Dates (the enhancement Heather mentioned) as that will show if something ended early or if something will most likely be delayed because the rest of the project is running late. My Creative and Dev resource managers love that since they don't usually have instead in how the project is doing until it gets to them. So totally helps with prioritizing work.