We accomplish something like this within a single project. The deployment schedule for the year gets a single task for each anticipated deployment with the appropriate date, and that pulls into calendars for long-range forecasting on certain clients. Once we get into the correct month, then the appropriate full project is built out, and the task marked complete in the forecast project.