Good morning all,
Myself and my colleagues have recently noticed that the months are not displaying on the Gantt chart view of any project we work on. As it has affected several of us, i assume this isn't a user error, but potentially a system change that has caused this.
Does anyone know how to display the months again in the Gantt Chart view? Please see attached a screenshot to see the current view (months should be displaying under 'Quarter').
Thanks in advance
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
@JamesWi7
Adobe seems aware - i see the same issue.
Thank you for contacting Adobe Workfront support.
Please note there is an ongoing defect for the missing month and day name from the Gantt chart in the task view.
and
. This is a known issue that our development team is currently investigating and working to resolve.
Thanks for sharing that!
Views
Replies
Total Likes
Views
Like
Replies