SOLVED

Filter a task report by task planned hours

Avatar

Level 2
Hi all, I need to create a filter for a task report to show all tasks with planned hours = 0. However, (task) planned hours does not seem to be available field for filtering the task report. Is there some workaround for this? Thanks!
1 Accepted Solution

Avatar

Correct answer by
Level 7

"Planned Hours" is available only for the column(view), For Filter you can use "Task > Work".

 

Hope this helps!

 

Please mark my response as "correct reply" if this helped you and to help others. Thanks in advance!

View solution in original post

2 Replies

Avatar

Correct answer by
Level 7

"Planned Hours" is available only for the column(view), For Filter you can use "Task > Work".

 

Hope this helps!

 

Please mark my response as "correct reply" if this helped you and to help others. Thanks in advance!

Avatar

Level 2

Thank you, @Srinija_N. Exactly what I was looking for. Much appreciated.