Duration is Defaulting to 0

Avatar

Level 3
When editing tasks, or adding tasks the duration is changing to 0 and the it doesn't show up in allocation. What is causing this? and how can I make it stop? Is it a bug? Or something I am doing wrong? Emily Byrne The Starr Conspiracy
5 Replies

Avatar

Level 10
Hi Emily, It's tough to tell without seeing it, but are the tasks you're editing Parent (Summary) tasks? Because if the children under it are all 0 Duration, the Parent/Summary will also be 0 Duration.

Avatar

Level 3
It is not parent tasks. It is just any new task that I add it defaults to 0. Or if I edit an existing task it will change the duration to 0. Emily Byrne The Starr Conspiracy

Avatar

Level 10
Hi Emily, I looked at a few things and couldn't find a simple reason for this (nor have I seen it happening here). I would give WF Support a call and they should be able to see your screen and walk you through some debugging steps. I'm betting it's something they can quickly identify by seeing it in action and checking different settings. Sorry I couldn't be of more help.

Avatar

Level 4
Emily and Vic, This happens when the default duration type is set to Simple. It will default to 1 Day for all other duration types. Like Vic, I would recommend Calculated Assignment as the default duration type you should use. I hope this helps!! David
DAVID A. TAYLOR Founder & Managing Partner

Avatar

Level 3
Thanks David. It is just weird because it would usually just default to the system duration. And I haven't changed any systems on the project setups. Its going to be a pain to change it all but I will look into that. Thanks!
-- EMILY BYRNE agile project manager o 281.785.1295 CHANGING B2B MARKETING FOREVER. "http://thestarrconspiracy.com/" style="color:rgb(17,85,204);font-family:Arial" thestarrconspiracy.com "http://blog.thestarrconspiracy.com/" style="color:rgb(17,85,204);font-family:Arial" blog | "https://www.facebook.com/StarrConspiracy" style="color:rgb(17,85,204)" facebook | "http://www.linkedin.com/company/the-starr-conspiracy" style="color:rgb(17,85,204)" linkedin Confidentiality Notice: This e-mail message is for the sole use of the intended recipient(s) and may contain confidential and privileged information exempt from disclosure under applicable law. Unauthorized review, use, disclosure, or distribution is strictly prohibited. If you are not the intended recipient, please contact the sender by reply e-mail and destroy all original copies of the message. Thank you. Check out The Starr Conspiracy in the "https://www.wsj.com/articles/taking-one-for-the-team-companies-foster-collaboration-1511885844" style="color:rgb(17,85,204)" Wall Street Journal