Hi WF Community,
Does anyone know if it's possible to display Baseline Task field data (e.g. Baseline Task Planned Hours - workRequired) on a project view?
I was thinking a collection maybe?
Since there can be many baselines for a task, the idea was to be able to view any or all task baselines for a given data point (e.g. baseline task planned hours) in a project view. We would then be able to see how the baseline planned hours has changed, for each task on the project, across each task baseline (1, 2, 3, 4, etc.). See attached screenshot.
I'm aware that a baseline task report can be created to display this data for each task's baselines, but our PMO is asking if they can view this in a project view, as opposed to a stand along baseline task report.
Thanks!