Why would our Planned Completion date field be missing from Requests?

Avatar

Level 4

All requests under this specific Request are missing the "Planned Completion Date" field. Previously, it would be there by default.

 

What would be the change that resulted into this field being removed from a Request? What settings should I look at to troubleshoot this?

stan255_0-1729133394127.png

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi,

 

In your queue settings, under Queue Details >> New Issue Fields, do you have "Planned Completion Date" checked?

 

Richard_Le__0-1729156960727.png

 

Best Regards,

Rich.

 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Hi,

 

In your queue settings, under Queue Details >> New Issue Fields, do you have "Planned Completion Date" checked?

 