Expand my Community achievements bar.

Do you have questions about the migration to Adobe Business Platform? Come join our upcoming coffee break and ask away!

Custom Planned Completion Date?

Avatar

Level 4

I am trying to create a task level view that displays the planned completion date by : the current duration divided by Project.Current # of Developers (Custom field at project level)..... Is this possible? I'm not having any luck today!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

5 Replies

Avatar

Level 4

OR to have my duration be custom? So # of Developers * # of Ideal Weeks (Both Custom Fields) = Duration...

If my Ideal Weeks = 70 & # of Developers = 4 .. My Duration should be 17.5?

Avatar

Level 7

Hi Jordan,

So let me make sure I'm understanding - if the duration is 10 days and there are 2 developers on the project, the custom duration would be 5 days and you would want a custom planned completion date field that adds the custom duration to the planned start date?

I think this should work but partial days aren't quite exact...

displayname=test

linkedname=direct

textmode=true

valueexpression=ADDDAYS({plannedStartDate},(DIV(DIV({durationMinutes},480),{project}.{DE:Current # of Developers})))

valueformat=HTML

Hope that helps!

Avatar

Level 4

THANK YOU!! Your understanding is accurate, yes!! This has certainly pushed me much further than I was but not sure it's there yet... If I'm looking at What if C @ 70 Weeks, I think I should be at 11/18/20 vs the 11/4/20 I'm seeing?

Avatar

Level 7

Hi Jordan,

Are you using a 5 day schedule or a 7 day schedule for your projects? If you are using a 5 day, the calculated field will include weekends so you will need to add an extra two days for each week the duration spans. This should get you closer:

displayname=test

linkedname=direct

textmode=true

valueexpression=ADDDAYS({plannedStartDate},(SUM(DIV(DIV({durationMinutes},480),{project}.{DE:Current # of Developers}),ROUND(DIV(DIV({durationMinutes},480),3.5),0))))

valueformat=HTM