I have a project report which counts the amount of tasks in a project using:
displayname=# of Tasks
textmode=true
valuefield=totalTaskCount
valueformat=HTML
Is there a way I can add another column which will show the amount of incomplete tasks too?
Topics help categorize Community content and increase your ability to discover relevant content.
Hi Steven,
Not that I know of, but in case it’s Close Enough (and works; untested), you could replace your valuefield line with
valueexpression=ROUND(((1-{percentComplete})*{totalTaskCount}),0)
Regards,
Doug
Views
Replies
Total Likes
‚Hi Doug.
I am afraid this comes out with some random data which I do not quite understand. There are lots of negative numbers in the result for example, but usually it still displays the total amount of tasks for the project, irrespective if they are complete or not.
Thank you for your attempt however!
Views
Replies
Total Likes
Ah: let's try that again, Steven (and this time, I've tested, as shown below).
What I overlooked initially was that Percent Complete is actually stored as an integer (e.g. 25) vs a decimal (e.g. 0.25), which is what led to the negative numbers you saw. So instead, the correct textmode for the (approximate) # of Open Tasks is as follows:
displayname=# of Open Tasks
textmode=true
valueexpression=ROUND(((1-({percentComplete}/100))*{totalTaskCount}),0)
valueformat=HTML
Regards,
Doug
Hi Doug,
Building on this clever idea, I've got a number of cases where my userbase have input tasks with 0 day durations and forgot to complete them. Since every other task is 100% complete, the math above flags there as being no missing tasks. Would there be any way to creatively tweak that math so it looked at the number of tasks where the Actual Completed Date was blank?
If it helps, I don't need a user-friendly display for the response. Just something an admin could look at and say 'Yes, we can batch close all of these projects at once.'
Katherine
Views
Replies
Total Likes
Glad you like it Katherine,
Excellent, subtle point. I invite you to try this version, which I just confirmed will ensure any Project missing even a single task (even one with with zero planned hours and zero duration) will detect and reveal such Stragglers:
displayname=# of Open Tasks
textmode=true
valueexpression=IF(ISBLANK({actualCompletionDate}),IF({percentComplete}=100,"Stragglers",ROUND(((1-({percentComplete}/100))*{totalTaskCount}),0)),0)
valueformat=HTML
Regards,
Doug
@Doug Den Hoed‚ You're a lifesaver! I thank you, though my Account team may be less fond. :)