Costs not showing up in Tasks

Avatar

Level 2

hi 

Im looking for some guidance for a project set up. I have costs against a user, however when when i create a tasks and assign them that to a user the Costs doesn't not show up in the report

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi,

 

Have you checked what cost type is associated with the task in the tasks finance settings? If you have a rate associated with the user's profile, the cost type will need to be 'user hourly'. 

 

Regards,

Rich. 