Hi: We found that because WorkFront limits you to only one occurrence of each milestone in a project, we no longer use their Milestone functionality, regrettably. There are a number of other features that use the WorkFront milestones (like Gantt charts) that we cannot take advantage of. I like these two options (and discard the others as being too problematic): 1) Break up your project structure, so that you have (your number 2, below): a. Create a program for the effort; b. One main project that does all the creation, proofing, testing, and certifying readiness to put into production; c. Have one small project for each Implementation; d. Associate all projects to the program; e. That way, each physical project will only have one WorkFront milestone of “Go-Live”; 2) Create a custom attribute that is applied to every task (we called ours “Standard Milestone”); a. Now you can assign any milestone as many times as you want; b. We have reports (Milestone Reports) that show all go-live events, grouped by week or month; c. We cannot use the built-in capabilities that use WorkFront milestones, but that hasn’t proven to be too much of a problem; Hope you are able to arrive at a solution quickly! Thanks, Eric