Can you report on the hours tracked by the user's assigned role in a project?

Avatar

Level 9

I am using an hourly report and instead of the hours being reported based on the 'assigned role' in a project, it's reporting it as the user's default role on their profile.

For instance, a project as a copywriter and a QC Resource. These are both members of the content team. However, one is assigned as a copywriter and one a QC resource.

My report is pushing everyone on the project as if they are a copywriter - vs showing the hours tracked by the assigned task of QC Resource.

주제

토픽은 커뮤니티 콘텐츠를 분류하여 관련성 있는 콘텐츠를 찾는 데 도움이 됩니다.

2 답변 개

Avatar

Employee

Hmmm, this sounds a little off. You might want to have support take a look at this one.

Avatar

Level 9

Me again - finding my question from years ago (again) so bumping it  up!