Hi All,
Our team has requested to see the date the first proof for a design project would be due when looking at and approving request. I think a calculated field would be able to capture that.
We currently have a field 'What tasks are needed for this project?' where graphic design is selected and another field 'Project Effort Level'. The project effort level (low, medium, high) indicates what template to use. Low has a duration of 3 days prior to first proof due, medium has a duration of 6 days, and high has a duration of 10 days. So if graphic design is selected and low is selected I think we would just need to add 3 days to the current date or entry date. Does anyone have any suggestions on how to best structure this calculation?